Results of the week in the project "Duyunov's motors"
The main focus at the "Sovelmash" construction site was on the engineering networks, for which intensive excavation work was being carried out.
The specialists commenced work on connecting the water supply chambers in the building. The chamber on the left side of the D&E is now waterproofed and on the right side of the building a concrete mattress has been made to install another chamber.
The storm drainage system is being looped around the side of the main entrance to the building. It has been brought to the outermost well. A pipe will be laid from there to the connection point of the SEZ's existing drainage system.
The installation of a chamber to introduce the heating supply into the building was also carried out.
The site is regularly cleared of the temporary road slabs and various waste items, which are taken away for disposal. At the same time, materials for the earthing circuit and lightning protection started to be delivered.
The surveyors started working on the site, so we can say that the landscaping work for the "Sovelmash" D&E has started.
Inside the building, the installation of elevators began.
The stator winding equipment was being installed and connected to the power supply. A power cable was being laid from the switchboard to the casting area.
SOLARGROUP has created a new roadmap for the project that shows the funding dynamics in real time. Besides, information on the key events from the project's history and the companies' main plans has also been posted there.
The roadmap is available here.
A major SOLARGROUP conference was held in Peru on May 27, attended by top managers Pavel Filippov, Pavel Shadskiy and the head of the "Resurs" production cooperative Andrey Lobov. We will report more about the event in the coming days.
We remind you that the following offers expire in May:
• +5% to the account top-up amount,
• +5% bonus shares for newcomers.
For more details, follow the link.
Hurry to take advantage of the beneficial offers!