Last week, work on constructing the building of the design and engineering technology department continued at the "Sovelmash" construction site:
- installation of the metal frame,
- installation of purlins (roof girders),
- placement of profiled sheets on the ceilings,
- installation of reinforcement frames for the office and amenity building foundations,
- installation of frames and formwork for staircases,
- concreting of the column foundation footings with the anchor groups for the production building along axis 6,
- unloading of the new batch of metal structures delivered to the site and much more.
The main scope of work on the metal frame installation is nearing completion. Soon there will be a new stage: the formation of interfloor overlappings. Before winter comes, it is necessary to close the thermal circuit of the building, to install and connect power supply and utilities. All the work will be done at the new, considerably higher prices. This means that the project requires a more intensive investment rate now. This was announced by Dmitriy Duyunov in his appeal to the project investors and partners. It is available here /news/posts/dmitrii-duyunov-o-neobxodimosti-mobilizovat-investirovanie-1934 .
The "Sovelmash" team, in turn, take all the necessary measures to successfully implement the outlined project goals. In the latest episode of the "Expert Time" program, Dmitriy Duyunov told about the company's plans for the production of angle grinders and miter saws using the combined winding technology "Slavyanka". "Sovelmash" already has preliminary agreements with the organizations that sell such tools, there are required premises, the laboratory is ready for accreditation. After the company starts selling its own original products, it will be able to receive substantial financial compensation from the state that will be used to build the D3333E.