"Sovelmash" construction site | Day 67

"Sovelmash" construction site | Day 67

In the new video, head of the information and analytics department Alexander Sudarev will talk about what has already been done recently at the construction site to erect the building of the design and engineering technology department (D3333E).

To date, work is underway to form the foundations: concrete work is being completed, waterproofing and sand backfill with layer-by-layer compaction is being done. The site has been prepared for the installation of large construction equipment, where, among other things, a crane will be positioned for the installation of the office and amenity building (O3333A). Transportation of metal structures has begun from the warehouse, and other activities are also in progress.

You will learn more by watching the video.

Enjoy watching!