"Sovelmash" construction site  Day 18

"Sovelmash" construction site Day 18

On the "Alabushevo" construction site, the work is underway on sand backfilling the pit with layer-by-layer compaction, concreting the staircase foundations, dismantling the formwork of previously cast concrete foundations, dismantling the formwork of staircases; waterproofing is being done on all the foundations, the installation of steel structures that form the building frame of the design and engineering technology department is in progress.