Breaking news with D. Duyunov
Exactly a year ago, on December 20, 2020, a video report was released against the background of the construction site pit summing up the work results for 2020. Now the year 2021 is coming to a close, and during this time, many significant events have taken place at the construction site where the "Sovelmash" D3333E construction is in full swing, and these achievements were preceded by serious work:
- concrete casting and completing the zero construction cycle;
- installation of metal structures for the D3333E building;
- installation of non-removable formwork;
- almost all the "maps" of the interfloor slabs have been cast on the 3rd floor of the D3333E building, including the largest one;
- fireproofing has started;
- installation of enclosing structures for the building interior has begun;
- one of the 2nd floor mezzanines has been cast;
- the installation of a firebreak, etc. has begun.
There have also been some technological advances in the project:
- casting motor rotors at the "Sovelmash" facilities;
- the built-in motor for the angle grinder made by applying the combined winding technology "Slavyanka" demonstrated excellent performance;
- other achievements that we talked about in previous videos.
The dynamics of workflow in "Sovelmash" is quite high and systemic. The project is developing, the D3333E building is not only getting an outline and a more complete look, but is also being "filled in".
There are 11 days left until the New Year 2022. Working routine continues, which will surely bring pleasant events to the "Sovelmash" project participants before the holidays.
Please hit the bell icon, subscribe to the official sources of "Sovelmash" that are listed below in order to be the first to learn about the nice and long-awaited events in "Sovelmash".
Follow our news carefully and leave your comments under this video!