Week results in the project "Duyunov's motors"
20 февруари 2022
New week - new achievements at the construction site where the "Sovelmash" D&E is being built.
• The builders have installed the exterior cladding of the office and amenity building face, except for the ramp, and are installing the cladding panels at the side of the building. This makes the building look more and more finished.
• The installation of roofing on the single-storey extensions has started.
• All of the stairwells have been fully cast.
• All concrete construction work has been completed. It remains to cast in concrete the first-level floor and cast part of the staircases.
• Part of the building has been treated with fireproofing. This will enable the installation of the building envelope, insulation and exterior panels to continue.
• A frame of interior partitions has been built on the third floor of the building .
• In the single-storey extensions, the builders are now working on the window openings.
Verification of the project participants has started operating normally in the back office. While the maintenance work was in progress, our specialists, among other things, were improving the verification service, which resulted in a line of requests. Now we are processing them again, but it takes longer than before. We appreciate your patience and understanding!
Gilles Weber, the national partner of SOLARGROUP in France, Côte d'Ivoire, Senegal, Benin, Togo, Cameroon and Burkina Faso, has arrived in Russia. We will tell you about his visit in the coming days.
Stay tuned for more news of the project "Duyunov's motors"!
• The builders have installed the exterior cladding of the office and amenity building face, except for the ramp, and are installing the cladding panels at the side of the building. This makes the building look more and more finished.
• The installation of roofing on the single-storey extensions has started.
• All of the stairwells have been fully cast.
• All concrete construction work has been completed. It remains to cast in concrete the first-level floor and cast part of the staircases.
• Part of the building has been treated with fireproofing. This will enable the installation of the building envelope, insulation and exterior panels to continue.
• A frame of interior partitions has been built on the third floor of the building .
• In the single-storey extensions, the builders are now working on the window openings.
Verification of the project participants has started operating normally in the back office. While the maintenance work was in progress, our specialists, among other things, were improving the verification service, which resulted in a line of requests. Now we are processing them again, but it takes longer than before. We appreciate your patience and understanding!
Gilles Weber, the national partner of SOLARGROUP in France, Côte d'Ivoire, Senegal, Benin, Togo, Cameroon and Burkina Faso, has arrived in Russia. We will tell you about his visit in the coming days.
Stay tuned for more news of the project "Duyunov's motors"!