Week results in the project "Duyunov's motors"
Last week, a significant event took place at the "Alabushevo" site where the "Sovelmash" engineering center is built. On December 13 and 14, working in two shifts, the builders cast one of the largest "maps" of the 3rd floor interfloor slab. A few days later, the concrete casting of one of the last two "maps" of the 3rd floor interfloor slab started.
The other scheduled activities were underway at the construction site too:
- one of the staircases was cast and the other was being prepared for casting,
- the firebreak made of foam blocks was built between the production and office3333amenity buildings,
- fireproofing the metal structures of the building frame was in progress,
- the enclosing structures of the inner part of the walls were mounted,
- the roofing work and other activities were carried out.
The "Sovelmash" D3333E building is becoming more and more complete. Now it is important to ensure timely funding so that the construction is completed as scheduled.
The project funding stage 16 has been extended until December 30 inclusive. If you missed out on investing in the project "Duyunov's motors" on the most beneficial terms, then take advantage of the stage extension. Along with going to project funding stage 17, the discount of shares will decrease and a number of special offers for investors will expire. The terms of the offers are available in the back office, the "Promo Offers" section. Or here /user/ref/materials