Week results in the project "Duyunov's motors"

Week results in the project "Duyunov's motors"

Last week, the construction of the "Sovelmash" D3333E passed the 80-day mark: that's how much time has passed from the start of installing the first girder to the installation of the last column of the testing and production building.

The construction of the office and amenity building is also underway:

- installation of basement floor slabs,

- reinforcement strapping for the first section of the elevator shaft.

Other work is also in progress at the construction site.

On August 25, the journalist and writer Alexander Sherstyuk, whose article marked the beginning of the project back in 1994, visited the construction site. Back then his article about Professor Nikolay Yalovega was published in the Zelenograd newspaper "41". Dmitriy Duyunov became interested in the article, he met Nikolay Yalovega, the author of the combined winding scheme for electric motors presented in the article, after which he continued working in this direction independently.

The journalist visited "Sovelmash", got acquainted with its management, visited the leased premises of the company as well as the construction site, where our camera crew filmed an interview with him.

On August 28, SOLARGROUP's national representative office opened in Nepal. To celebrate this, an online conference was held with the participation of SOLARGROUP's top managers Pavel Shadskiy and Pavel Filippov, national partner in India and Nepal Gulshan Kumar Birdi, CEO of ASPP Weihai Victor Arestov. During the first day, the conference was viewed by more than 1,200 people. We will tell you more about the event in the coming days. Follow our news!