Week results in the project "Duyunov's motors"
Over the past week, the work completing the zero cycle of the design and engineering technology department construction was carried out on the "Sovelmash" construction site:
formation of the foundation for the office and amenity building (O3333A),
waterproofing the foundation,
backfilling with sand by applying layer-by-layer compaction.
Soon, the builders will start installing the O3333A metal frame. A site has been prepared for the large construction equipment that will participate in installing this part of the building. The transportation of metal structures from the warehouse began.
The main construction work continued throughout the past week too:
installation of metal structures,
roofing work,
installation of formwork and more.
Investing in the project has become even more affordable for Russian citizens. According to numerous requests, the opportunity to purchase a package with the nominal value of $ 250 is available in the back office until September 1 inclusive, both in a lump-sum payment and through a 10-month installment plan.
SOLARGROUP partners can now additionally contribute to funding the construction of the "Sovelmash" engineering center. Previously, partners could either withdraw their referral remuneration, or purchase investment packages with it. Now they can direct it to "Sovelmash" and receive investment shares as a bonus: 10 shares for each transferred $1. In order to take advantage of this opportunity, find the corresponding banner on the main page of the back office and click the "Find out more" button. The banner can only be seen by the partners who receive referral remuneration. Let's accelerate the "Sovelmash" D3333E construction, everything is in our hands!