Results of the week in the project "Duyunov's motors"
"Sovelmash" D&E construction
The deadline for the D&E completion report, scheduled for the end of March, is approaching. Therefore, all the efforts of "Sovelmash" were primarily focused on the completion of the internal engineering networks.
• The installation of the ventilation system and cooling equipment continued last week.
• A lot of heating, ventilation, lighting, and power supply work was done on the third floor.
• Floor screeding was also carried out there.
• The freight elevators were put into operation. The lifting of equipment to the third floor started.
• Installation of air heat curtains in antechambers and gateways began.
• Equipment was installed in the control room and many other tasks were carried out.
Preparing to obtain a construction completion certificate
The specialists of "Sovelmash" continued to form packages of documents to apply for the completion of construction.
After March 10, representatives of the regulatory authorities will be working in the building to make comments that we will have to address before submitting an application for the construction completion certificate.