Results of the week in the project "Duyunov's motors"

Results of the week in the project "Duyunov's motors"

The construction of the "Sovelmash" design and engineering technology department proceeded simultaneously on many fronts.

• Inside the building, electrics were wired, tiles were installed, interior walls were finished, and ceiling parts were painted.
• The ventilation system, pipework, fire sprinkler system and others were installed.
• The installation of the heat distribution point continued.
• Work was underway on the pit through which the storm sewer connection will be made.
• Backfilling of the heating pipeline was carried out.
• Work was in progress next to the platform for the air conditioning systems, which will soon be installed in their place.
• The temporary fence was completely removed and a permanent fence is to be installed to replace it.