Production line start-up and other activities at the "Sovelmash" construction site
    In the new video report, Dmitriy Duyunov gives a tour of different areas at the construction site and talks about the construction progress of the design and engineering technology department. 
Watch the video by clicking here. 
• The site next to the D&E is being prepared for asphalt paving. The area is being cleared of unnecessary materials and excess soil. 12,000 cubic metres of soil will need to be removed. 
• The grounding terminals have been made and the installation of pipes for power supply will begin shortly.
• The work on the engineering networks is nearing completion.
• The installation of elevators in the building is about to be completed. 
• The staircase shafts are being finished.
• The automated production line is scheduled to be put into operation in June to start producing the first batch of combined winding motors. 
• The hub motor blanks have been made.
The timing of completing the D&E construction depends on the investment pace. The project implementation rate is now entirely in the hands of the investors.