"Sovelmash" D&E today: installation of cooling system and other activities
In a new video from the "Sovelmash" construction site, Alexander Sudarev explains what kind of tasks the construction workers are carrying out today.
• The cooling system components have been unloaded, and its assembly is in full swing.
• There are more and more engineering networks above the ceiling: electrical carriers, cooling and smoke extraction systems, supply ventilation systems.
• A permanent lighting system is being installed.
• Radiators have been mounted along the walls.
• Finishing work, including tile installation, is in progress.
• There are new machine tools.
• Finishing materials and ventilation ducts have been moved to the third floor thanks to putting the freight elevator into operation.
Watch the video by following the link.
Invest in the project to become a co-owner of the innovative enterprise!