"Sovelmash" D&E today: installation of cooling system and other activities

"Sovelmash" D&E today: installation of cooling system and other activities

In a new video from the "Sovelmash" construction site, Alexander Sudarev explains what kind of tasks the construction workers are carrying out today.

• The cooling system components have been unloaded, and its assembly is in full swing.

• There are more and more engineering networks above the ceiling: electrical carriers, cooling and smoke extraction systems, supply ventilation systems.

• A permanent lighting system is being installed.

• Radiators have been mounted along the walls.

• Finishing work, including tile installation, is in progress.

• There are new machine tools.

• Finishing materials and ventilation ducts have been moved to the third floor thanks to putting the freight elevator into operation.

Watch the video by following the link.