Results of the week in the project "Duyunov's motors"

Results of the week in the project "Duyunov's motors"

"Sovelmash" D&E construction

• "Sovelmash" obtained a permit for power input for a 10 kV line, issued after the comments of the technical supervisor had been eliminated. This is a crucial step for obtaining the certificate of construction completion.
• The protective layer of asphalt was removed, after which the ground is to be levelled and compacted, and the finish surface coating is to be laid.
• The site fence was moved to make its location consistent with the project plan.
• Entrance gates were installed, all communications for connecting automated systems were prepared.
• Four charging stations for electric vehicles were installed.
• Transparent panels arrived at the site for the construction of a noise shield.
• Improvement of the site is in progress: planting of red maple trees, installation of kerb stones and other activities.
• Inside the building, active work shifted to the upper floors. Ventilation equipment, electrical wiring, permanent lighting, automation control panels, etc. were installed there. Interior finishing reached the final stage.
• The office for the accounting department was prepared to accommodate the staff.
• "Sovelmash" started the final stage of relocation from the leased premises to the D&E.

"Sovelmash" developments

• Negotiations were held on the development of an import-substituting drive and equipment for its production to benefit the automotive industry. The schedule and first steps were outlined.
• Work continued on the motor for the "Moth" quadcopter. Assembly of the landing gear and formation of the wings began.
• Work was underway on a water-cooled German traction motor. The winding was done.

SOLARGROUP webinar

On June 5, at 17:00 Moscow time, a live broadcast with the SOLARGROUP management will be conducted. Sergey Semyonov, Pavel Filippov and Sergey Shevchenko will report the news and plans, sum up the interim results and answer your questions.

Register by following the link.

Current offers

Let us remind you of the offers that will boost your benefit from investing in the project.

5% discount on payments of $ 100 or more for early repayment up to and including July 31.
Friendly promo code for 10% of bonus shares when buying a new package, until the end of stage 19.

Information about all the offers in the project is available in the back office.

Use and invest with maximum profit!

INVEST