Results of the week in the project "Duyunov's motors"
"Sovelmash" D&E construction
Last week, the installation of ventilation and other engineering networks continued, as well as interior finishing on a number of floors. Many other activities were in progress, too.
• Welding of pipes and piping of the cooling plant collector was carried out.
• Smart film was mounted on the windows of the exhibition hall in the O&A building.
• Finishing of the ceiling over the entrance bay window in the office and amenity building and the installation of exterior lighting were completed.
• Lighting was installed in the area where the design engineers are now working.
Developments by "Sovelmash"
• Electric motor housings for quadcopter were produced using the in-house equipment.
• The first angle grinder controller board was "baked" in the furnace. The quality of soldering the components is good.
• The commissioning of a universal heavy lathe was carried out.
• New materials and equipment arrived.
Your investments help accelerate the construction of the "Sovelmash" D&E, bringing the launch of the enterprise and the deadline for getting the dividends closer. In March, beneficial offers are available for all categories of investors. Please click here to learn more about them.