Key events of the week in the project "Duyunov's motors"

Key events of the week in the project "Duyunov's motors"

"Sovelmash" D&E construction

Over the last week, internal finishing and work on the internal engineering networks was well underway in the design and engineering technology department.

• The installation of turnstiles at the entrance hall of the office and amenity complex started.
• The installation of suspended ceiling in the first-floor hallways of the O&A began.
• Cladding of the elevator area on the first floor of the O&A was carried out. The elevators were aligned with the floor marks on each floor.
• The glass partitions of the 1st floor offices were covered with a frosted film. They're being settled in by the staff. Partitions and doors were installed on the second floor of the O&A.
• A large volume of finishing materials was purchased and delivered.
• Ventilation was installed in the production area.
• The busbar system was installed in the stator winding area.
• The cold water supply system was pressure-tested.
• Heating was put into operation in the rooms intended for taking meals by the employees of the production area.
• Debugging the software for the heat distribution unit controller was completed.
• The workers started equipping the second warehouse.

Moreover, "Sovelmash" continued to prepare packages of documents to apply for the completion of construction.

It is now necessary to accelerate the project funding in order to complete the D&E as soon as possible. Every investment you make is a step towards the success of the project!