Results of the week in the project "Duyunov's motors"

Results of the week in the project "Duyunov's motors"

News summary from the "Sovelmash" construction site

• The floor screed on the first level of the office and amenity building was completed. This work is in progress on the first floor of the production building.
• Heating radiators were being installed in the stairwells.
• Some parts of the pipework for the automatic fire extinguishing station were welded.
• The removal of the temporary road slabs was completed along the left side of the building.
• The earthwork was underway. Waterproofing of the trays for the heating pipeline and joining the old heating pipeline to the new one were carried out.
• Another batch of asphalt concrete was unloaded at the ramp and the first layer was put.
• Installation of the kerbstone started.
• The rains seriously complicated the progress of landscaping and have impeded connecting the storm drainage system to the central pipe manifold for the time being. Water had to be pumped out at the site on a regular basis.

In addition to the D&E construction, "Sovelmash" was engaged in developing and manufacturing machine units, tooling, and also working on the angle grinder.

We have updated the roadmap of the project to include a video on the D&E construction progress, as well as more detailed information on the funding stages. View it here.

According to the counter on the roadmap, there is less than $ 8 million left to complete funding for the project. And we can do it even faster and in bigger amounts! Until August 15, the "Thank You" offer is running in the project, which is needed to complete the main scope of construction work before the cold weather. It is profitable for absolutely each and every investor in the project.