Results of the week in the project "Duyunov's motors"
Last week, the "Sovelmash" D&E was actively preparing for the launch of its automated production line. It is scheduled to be launched in June and to start production of the first batch of combined winding motors.
The site next to the D&E has been cleared of excess soil and unnecessary materials in order to proceed with asphalt paving. The road has been dismantled.
The ground leads have been completed to start installing power supply pipes.
Inside the building, the elevators are being completed and the staircase shafts are being finished.
Watch the video tour given by Dmitriy Duyunov around the different areas of the construction site to find out how the work is progressing.
On June 14, equipment and fire-resistant glazing were delivered to the site.
Finishing work on the third-floor walls in the O&A building and the installation of supports for the transparent interior partition walls are in progress.
A new construction stage has begun - the installation of internal engineering networks. For more details, watch the video here.
Also, the D&E had a full-scale clean-up with wet and dry cleaning, including washing the walls.
Other activities are also well underway: waterproofing, concrete bedding, preparations for water supply, and so on.
For more details on how the work on water utilities is progressing, watch the interview with a representative of the subcontractor for "Sovelmash".
The most extensive work is in progress continuously and you can find out more about it in this video.
In the meantime, the project has the "Minus 1 step on child packages" offer running until June 30 inclusive. Hurry to read more about the conditions to start building a financial foundation for your children now.
There are other offers for investors and partners to ensure that each of you can get the most out of the project - and accelerate its implementation. Choose the offer that suits you and get your bonuses.
SOLARGROUP continues to hold events around the world and increase the number of participants and supporters of the project "Duyunov's motors". Watch the video to see what it was like in Latin America.
Furthermore, the first week of Solar Race 2023, which features a tuk-tuk with a "Slavyanka" powered motor, is coming to an end. Don't forget to give your support to our team! The guys are now in the first competitive stage of the race with the finish line at Baikonur Cosmodrome, you can find all the details of the race on the channel.
Events in the project are developing dynamically, stay tuned!