"Sovelmash" construction site | Day 141

"Sovelmash" construction site | Day 141

In the new video from the construction site, you will see the changes that have taken place recently.

The roofing work continues - the sealant is being fitted and covered with the final elements of the roofing, the staircases have been cast in concrete, which will enable us to proceed with covering the middle part of the building with the roofing, thus completing the installation of the main part of the roof.

The 3rd floor is almost ready for casting the interfloor concrete slabs. The amount of enclosing structures on the territory of the temporary warehouse is growing and their installation is being carried out.

At the 1st floor level, the pits are being finished, concrete work is being done, the reinforcing frame is being bound for the concrete work, and many other activities are in progress.

For more details, watch the video. Enjoy watching!