Start of pouring the finish flooring in the "Sovelmash" D&E

Start of pouring the finish flooring in the "Sovelmash" D&E

Almost all of the doors, including the sliding automatic ones, are installed in the office and amenity building.

Preparation for finishing is underway: some of the columns have already been covered with special material and glass doors have been installed.

On the third floor, quite a lot of interior partitions have already been installed, antechambers are being shaped for the further installation of ventilation equipment, and other activities are also in progress.

At the D&E testing and production site, waterproofing of the first-level floor, specifically the concrete bedding, continues. And the long-awaited event for all the project participants - the pouring of concrete begins in the right side of the building, including the one-storey extension, where the heating equipment will be installed in the future to supply heat to the building. Closing the thermal envelope in the D&E and carrying out concrete construction work is the top priority before the onset of cold weather.

Watch the video from the "Sovelmash" D&E construction site at https://youtu.be/dTmbUIujvzk. Be the first to find out about the company's events!