Container from China and the construction completion certificate: report from "Sovelmash"
Today a package from China has been delivered to the "Sovelmash" construction site. In the container, there are revolving doors for the first floor hall, a unit for winding toroidal cores and other useful items.
Watch the video with Alexander Sudarev to find out about the construction progress and preparations for in-house production.
• Work on the ventilation utilities are underway in the heat distribution unit.
• Finishing work is underway in the sanitary conveninces and tiling is being done.
• The interior partitions have been mounted on the second floor of the office and amenity building.
• Floor screeding, installation of the ventilation and heating systems are in progress on the third floor of the production area.
The specialists of "Sovelmash" are working hard to prepare the documents to apply for the construction completion certificate.
The construction pace now depends on the inflow of investments.