Week results in the project "Duyunov's motors"
Despite the difficult weather conditions, the work is in full swing in various areas at the construction site where the "Sovelmash" D3333E is being built.
• The installation of the roof continues where the elevator shafts are located, as well as in the points of the staircases exiting to the roof. Most of the roofing work has already been completed.
• Casting the 3rd floor interfloor slabs is underway. Several maps are fully cast. Preparations for casting the 2nd floor interfloor slabs continue: reinforcing mesh and reinforcing frames are being laid, they are being strapped and prepared for further heating.
• Staircases and steps inside them are cast with concrete. The covers of the elevator shafts have been cast.⠀
• The internal parts of the walls are being mounted.
Work is also underway on the leased premises of "Sovelmash". In particular, the company's specialists are working on the development of their original equipment for mounting the stator winding of angle grinders. And this is only one area of work.
Adding funds to the account via the Perfect money payment system has been disabled in the back office. You can use alternative methods. The manuals for the most popular payment systems are available in the "Help" section, the "Questions3333Answers" subsection. Or by following this link /faqs?f=1
The offer for investors to increase investment packages has been extended until the end of stage 16. To recap: if you pay in installments, then, within the framework of the offer, you can increase the paid package to a package of any denomination on the purchase terms. Thus, you will increase the number of your shares at the most profitable discount available in the project today. Find out how to use the offer here
The offer expires on December 15. Hurry to increase the number of your shares in the project on beneficial conditions!