On the construction site in the SEZ "Technopolis "Moscow", the construction of the "Sovelmash" design and engineering technology department is progressing in accordance with the established procedure. This week, the following activities continued:
- installation of metal structures for the office and amenity building,
- casting of staircases,
- roofing work,
- preparation of the warehouse for accepting the enclosing structures and much more. ⠀
Equipment for setting up the automated production line to make the "Slavyanka"-based motors has been delivered to the "Sovelmash" territory in Zelenograd. Despite the difficulties and delays in delivery from China due to Covid-19 restrictions, the equipment for the "Sovelmash" D3333E has arrived at the prepared premises. The installation process will begin soon.
The "Sovelmash" specialists continued work on the modernization of the Milwaukee angle grinder (UShM). The factory commutator motor was replaced with an induction electric motor based on the "Slavyanka" combined winding technology manufactured by "Sovelmash". After that, the motor tests began.