Week results in the project "Duyunov's motors"

Week results in the project "Duyunov's motors"

Last week the construction of the "Sovelmash" design and engineering technology department continued at the construction site in "Technopolis "Moscow".

-The erection of metal structures for the future office and amenity building started.
- The formation of staircases was carried out, including: reinforcement strapping, installing removable formwork, preparations for casting concrete.
- Roofing work started in the testing and production area.
- The earthwork continued: layout of the sewage system along with testing individual sections for leaks.
- Unloading of construction materials.

The "Sovelmash" specialists compared two angle grinders (UShM): a standard one by "Interskol" with a commutator motor and the same UShM modernized by applying the combined winding "Slavyanka" technology. The comparative tests revealed that the "Slavaynka" based UShM cuts metal faster, is more comfortable to operate due to a lower noise and vibration level.
Watch the test video here - https://youtu.be/7LfZLwJakGA

A national representative office of SOLARGROUP opened in Italy: the 16th in the world and the 6th in Europe. To celebrate this event, an online conference was held with the participation of the company's top managers and leading partners as well as the top officials of the project. The audience was addressed by: Pavel Filippov, Pavel Shadskiy, Victor Arestov, Andrey Lobov. As well as Birdi Gulshan Kumar, who has become the national partner of SOLARGROUP in Italy. We will tell you more about the event in the coming days. Follow the project news!