Week results in the project "Duyunov's motors"

Week results in the project "Duyunov's motors"

The news of the outgoing week is related to the construction of the "Sovelmash" D3333E.

The construction of the building foundation has begun! To do it, the concrete slabs are poured using B 7.5 concrete on which in the future the main foundation "floors" will be built using B 25 concrete: formworks will be made and reinforcing mesh will be set up for them too. At the same time, all the measures required at low temperatures are taken: antifreeze additives are added to the concrete, each slab is covered and heated, the temperature and degree of concrete setting is measured.

Besides, some other works are underway at the construction site:
- trucks with the metal structures for the building frame produced by Astron are being unloaded;
- the ground in the pit is being warmed up, the degree of thawing is being controlled;
- outdoor lighting is being installed.

The construction activities are being carried out in full accordance with the schedule. We will inform you about the further progress of the work. Follow our news!