"Sovelmash" D&E construction

"Sovelmash" finished its operation on the leased premises and completely relocated to the building of the design and engineering technology department. The offices on the second floor of the office and amenity building were put into use, furniture and equipment for the press office and studio, the accounting department, and the office of one of the company's deputy CEOs were arranged.

Besides, furniture and equipment were delivered to the second floor lobby of the O&A. Finishing work is being completed there.

Interior finishing on the third floor was well underway, including the installation of floor tiling.

The O&A was cleaned from the outside of the building.

Work continued on the installation of ventilation and cooling systems, the second water supply tapping, construction of a protective screen on the site and other tasks, including the preparation of documents for obtaining the certificate of construction completion.

Developments and equipment

Equipment for the SMD assembly line for microelectronics components was delivered.

The motor for the "Moth" quadcopter was prepared for preliminary tests.

Live broadcast with the SOLARGROUP management team

On June 5, a webinar was held with the participation of the SOLARGROUP management: Sergey Semyonov, Pavel Filippov and Sergey Shevchenko. The live broadcast covered the interim funding results, project's news, legal aspects of the company's operation, and the final funding stage. The speakers also answered questions from the investors.

Watch the recording here.

Current offers

Let us remind you of the offers that will increase your benefit from investing in the project.

A 5% discount on payments of $ 100 or more for early repayment up to and including July 31.

The opportunity to restore installment plans canceled in 2019, up to and including June 30.

Friendly promo code for 10% of bonus shares when buying a new package until the end of stage 19.

Information about all the offers in the project is available in the back office.

Use and invest with maximum benefit!

INVEST