Results of the week in the project "Duyunov's motors"
"Sovelmash" D&E construction
Preparations for obtaining the completion certificate were actively underway at the construction site during the week.
• Work began in the second room of the cooling plant, where the small heat exchangers are to be placed.
• The refinements necessary to provide permanent circuit electricity were carried out.
• The foundations for the noise shield were constructed on the border between the "Sovelmash" site and the gardening cooperative.
• Internal finishing, installation of the ventilation system and other activities were underway.
Roadmap updates
We made the roadmap more informative and user-friendly.
The following features have been added:
• planned and attracted investments by month in 2024,
• graph showing the growth in the investment share price from stage 1 to stage 19,
• investment volume and number of new investors by year.
We remind you that the roadmap displays real-time dynamics of investment inflow and the amount that needs to be collected in order to put the "Sovelmash" D&E into operation and go to the final funding stage.
Current offers
Let us remind you about the offers that will increase your benefits from investing in the project.
10% discount on payments of $ 100 and more upon early repayment until May 31 inclusive.
Friendly Promo Code for 10% of bonus shares when buying a new package until the end of stage 19.
Information about all the offers in the project is available in the back office.
Use and invest with maximum benefits!