Results of the week in the project "Duyunov's motors"

Results of the week in the project "Duyunov's motors"

"Sovelmash" D&E construction

• The main focus of construction now is on the external engineering networks. Installation of ventilation and smoke extraction systems, thermal insulation of hot water supply pipes were in full swing.
• The offices on the ground floor of the O&A are about to be settled in. On the second floor, the partition walls are installed and interior finishing is in progress. On the third floor, the construction workers were preparing to install interior glass partitions.
• Decorative wall and ceiling panels were installed in the O&A building.
• Sockets and switches were installed.
• Fire cabinets were connected.
• The equipment in the shop was connected to the power supply mains.
• Regular and thorough cleaning of the area was carried out, making the D&E much cleaner than a standard construction site. This is needed primarily to protect the equipment from dust.

"Sovelmash" continued to prepare documents to obtain the construction certificate of completion.

Every effort is being made to speed up the construction and put the D&E into operation.


SOLARGROUP offer

We have launched the opportunity to upsize a fully repaid investment package up to and including March 31.

This offer is the most beneficial offer for you if your repaid package was purchased in the early stages of the project funding.

The opportunity is already available to you in the back office. Hurry up to take advantage of it!

UPSIZE A PACKAGE