Results of the week in the project "Duyunov's motors"

Results of the week in the project "Duyunov's motors"

Construction of the "Sovelmash" engineering centre

Despite the snowfall, work at the site kept on going.

• The storm drainage pipe was cut into the central sewer. That was followed by backfilling the pit and forming the storm drain manholes in the area of its connection to the sewer.
• The fencing was installed on the front side of the site. The site is now enclosed by a fence on two sides.
• Installation of manholes and putting manholes on the mark where asphalt had previously been paved was in progress.
• Work started in the water treatment area. The water pipe is to be inserted into the connection chamber.
• Central system ventilation and air conditioning were installed, namely in the rooms of the office and amenity building. The climate control system was installed in the antechamber of the O&A building.
• The assembly of railings and interior finishing work continued in the D&E. The installation of lighting on the staircases was almost fully completed.

SOLARGROUP news

The interface of the roadmap for the project "Duyunov's motors" was updated. We added more information about the performance of SOLARGROUP and "Sovelmash" by year with hyperlinks to the posts about each event. The roadmap was also supplemented with photos that show the construction dynamics for the "Sovelmash" engineering centre.

Watch and share with other partners.

We remind you that the first round of the SOLARGROUP lottery ends on October 31. Everyone who's got coupons for investments in October will participate in a raffle of a "Slavyanka" based motorcycle and bonus investment shares. More details.

Hurry up and get more coupons!

INVEST