Results of the week in the project "Duyunov's motors"
The "Sovelmash" construction site has been considerably transformed over the past week. It's safe to say that most of the earthwork is done now.
• Work on asphalt paving at the construction site was well underway.
• The use of the left hand entry area to the site was restored.
• A pit was excavated in the right hand entrance area and work on drilling under the roadway to the storm sewer connection point commenced.
• Supplies for setting up the ventilation system were delivered.
• Installation of the fire sprinkler system and finishing work continued in the building.
• In order to accelerate the D&E construction pace, we have extended the "Thank You" offer up to and including September 15. In the previous month, the offer helped attract a record-high amount of investments in the project. The investors could see the results of this at the construction site quite soon.
But the primary goal of the offer is still ahead of us. We need to attract $ 4,000,000 to complete the major construction work before the cold weather sets in.
The terms and conditions of the "Thank You" offer, examples of benefits and videos explaining the details are available in the back office.