A number of landmark events took place in the "Sovelmash" D&E construction last week.

The landscaping of the area outside the construction site, where the water supply system had previously been tapped, started. The ground was levelled and trees were planted. Besides, the parking area was paved with asphalt.

All four passenger and cargo-and-passenger elevators were delivered to the D&E. Once they are installed, the costs of lifting loads to the upper floors will be substantially cut.

Two trucks of reinforced concrete for the on-site part of the heating distribution network were also delivered to the site, as well as a lorry with power equipment,
concrete slabs for engineering work with external utilities and other materials.

For the latest news on the "Sovelmash" D&E construction, see this link.

Follow our news and stay tuned for the progress of the project "Duyunov's motors"!