Results of the week in the project "Duyunov's motors"

Results of the week in the project "Duyunov's motors"

The "Sovelmash" D&E construction pace has considerably increased lately. The work is being done simultaneously in different areas.

Last week, the construction workers poured the protective layer in the warehouse part of the building for the most extensive "map" in the entire duration of the concrete construction work.

The last concrete layer was poured in the office and amenity building. It now remains to apply a finish coating on top.

A temporary heating circuit was connected on the first floor to maintain the temperature required for concrete.

Outside the building, the construction workers were preparing to pour concrete for the loading ramps and footings for the climate control equipment.

Work on the engineering utilities commenced:

• preparations to install a storm drain system,
• preparations to install power transformers, two of the four foundations for which have already been cast, as well as to install the switchboards - once this work is completed, it will be possible to proceed with power supply installation.

Dmitriy Duyunov speaks in detail about the construction progress in the video from the construction site, available by following the link.

On October 9, a major SOLARGROUP conference was held in Hanoi, Vietnam. It was personally attended by the company's executives: Sergey Semyonov, Pavel Shadskiy and Pavel Filippov, as well as the founder of "STIIN" Andrey Lobov. We will tell you more about the event in the coming days. Follow our news.