Results of the week in the project "Duyunov's motors"
The "Sovelmash" D&E building is being prepared for the onset of cold weather in full swing, engaging a large number of construction teams. On the first floor of the testing and production building, the builders are performing waterproofing, pouring a protective layer of concrete and installing a two-layer rebar grid. Then the finishing concrete layer will be poured.
The thermal envelope of the building is virtually closed. There are two remaining tasks left: the airlock on the third floor and the ventilation grilles. The latest video from the construction site is available by following the link.
The D&E building has approached the fall and winter period well prepared. This became possible thanks to the competent work of the "Sovelmash" and SOLARGROUP teams and the support of investors. This includes a fundraising offer to collect funds for the engineering utilities. Last week its results were summed up. The main goal of the offer - to raise $ 3,000,000 - has been accomplished. The amount of 95,031,061 rubles (at the rate of 55-60 rubles per dollar) was handed over to "Sovelmash".
Now the task of every investor who bought an investment package in installments is to make timely payments in order to support the construction and get the bonuses in full!