Results of the week in the project "Duyunov's motors"

Results of the week in the project "Duyunov's motors"

Casting the concrete bedding in the "Sovelmash" D&E has been completed. The builders cast the first floor of the office and amenity building. 

Soon the specialists will start pouring concrete for the final flooring. 

The installation of the outer wall and roof cladding is nearing completion; the columns, ventilation grilles and metal frames for installing the ventilation equipment are being mounted. 

"Sovelmash" received the first elevator motor parts. In 3 months, these motors had been developed, the drawings - made, and the parts - ordered. As planned, in mid-July "Sovelmash" will begin testing the first inhouse-designed original elevator motors. 

The company's specialists continued to set up the production of angle grinders (UShM). The "Sovelmash" Trading House has already received preliminary applications for the production of 6,000 angle grinders. 

The contest of reviews about the project "Duyunov's motors" has started. Are you the project investor and want as many people as possible to know about the project and participate in it?

Record a video review telling the world why you're investing in the project and get up to $ 1,000 for the best review. The contest conditions can be found by following the link


We remind you that you can profitably increase the number of your investment shares in the project thanks to the new offer. When buying a new package or increasing your current package, you will receive up to 50% bonus shares of their total number in the package. More about the offer

Registration for the SOLARGROUP International Conference, which will be held on August 6 in Moscow, Russia, continues in the project. There are 110 spots left. You can find out more and pick up your ticket here.

Follow our news and stay informed about the development of the project "Duyunov's motors".