2 years of "Sovelmash" D&E construction: interim results in numbers
What has been done since the construction of the "Sovelmash" design and engineering technology department (D&E) began, i.e., since December 2020?
Most of the construction work has been accomplished.
• The foundation and metal frame of the building have been completed.
• The thermal envelope of the building has been closed since the roof, walls, windows, exterior doors and cargo door have all been completed.
• All the staircases, elevator shafts and interfloor ceilings have been finished.
• The first-level finish flooring is 90% complete.
• The installation of interior partitions is in progress. They are 90% complete.
Work has begun on the engineering utilities to connect the building to the heating pipeline, electricity and water supply, and provide sewerage.
Besides, "Sovelmash" has purchased and transported engineering and technological equipment to the D&E. Moving and installing equipment from the leased premises to the permanent work location is underway.
We have summed up the interim construction results in May 2022, they are available here.
If you compare them with the current state of the construction site, you can see the progress of the D&E construction over the past six months.
What activities are left for the builders to complete?
• Connecting the engineering utilities, installing heating equipment, connecting power transformers.
• Purchasing pumping units, elevators, power supply facilities, etc.
• Completing the finish flooring.
• Completing the installation of interior partitions.
• Executing vertical alignment, roads, parking lots, landscaping and other activities on the site.
Everything is being done to complete the construction as soon as possible. Now the construction site can deploy the entire amount of funding. Therefore, the construction rate depends on the rate of funds flowing in.