2 days before New Year: report from the "Sovelmash" construction site | Day 206

2 days before New Year: report from the "Sovelmash" construction site | Day 206

We continue the series of New Year's Eve videos about the work on the construction site where the "Sovelmash" D&E is being built.
 
 Until December 29 inclusive, the Astron builders carried out the installation of enclosing structures, namely the internal parts of the walls. The one-story extensions were completely covered, the 3rd floor was also almost completely covered, and the openings were left for lifting equipment, tools and materials. 
 
 The roof of the building is almost completely covered. The construction crews under the management of the general contractor HAKA MOSCOW were engaged in the construction of the firebreak between the office&amenity and testing&production parts of the building, the preparatory work was carried out prior to concrete casting both the interfloor slabs and staircases. The installation of removable formwork on the last flight of stairs of the testing and production part of the building started.
 
 The builders approached the completion of 2021 very competently. Most of the tasks were completed. Engineering equipment, heat engineering equipment, transformers, ventilation equipment were delivered to the site, and this became possible thanks to the timely conduct of preparatory work. 
 
 The work schedule for the coming year has already been drawn up. The builders will start work on January 4, 2022. 
 
 Keep following our news. Happy New Year!