"Sovelmash" D&E construction in numbers: 15,000 sq.m. of the concrete floor poured in 2 months

"Sovelmash" D&E construction in numbers: 15,000 sq.m. of the concrete floor poured in 2 months

In a new report from the construction site you will see an interview with the representative of "Evrospetspol". He will explain the main features of the D&E floor. You will also learn about the construction progress.

Over the past 2 months, 15,000 square meters of the concrete floor has been poured on the first floor of the building. This opens up a new front of work. So, in the near future the builders will mount the interior partitions and begin installing the equipment. 

Some other activities are also underway at the construction site. 

• The ramp unit has been completed, and the site is being prepared for concrete casting. 
• The partitions are being installed on the second floor of the office and amenity building, and all the necessary materials have been delivered for this purpose.

Watch the video for more details.

The "Sovelmash" D&E construction pace now depends largely on the volume of funding. Each investor can bring the commissioning date closer, for example, by early repayment of their installment plan.

READ MORE NEWS