Pouring a floor screed in the "Sovelmash" D&E
Watch the latest video content from the "Sovelmash" construction site.
Next to the O&A, a concrete pump has been connected for further pouring of a floor screed. Before that, a special covering was spread over the area, the heating utilities were installed, and electrical wiring was made on the floor.
Once the concrete is poured, it will be possible to proceed with the tiling and the installation of interior glass partitions.
The old heating pipeline is being connected to the new one.
Another batch of asphalt concrete is being unloaded at the ramp, and the first layer has already been installed.
Installation of the kerbstone has started.
Many other activities are in progress, including the development and production of machine units and tooling; work on the angle grinder is in progress.
We remind you that now everyone has the opportunity to make a contribution to the construction of the design and engineering technology department. Make your investment as profitable as possible by using the "Thank You" offer that has been launched in the project and is in effect until August 15 inclusive. More details about the offer.