"Sovelmash" construction site | Day 78
24 August 2021
At the moment, new axes have been installed on the construction site, and now the testing and production part of the building practically borders on the territory of the office and amenity building, where the installation of the basement slabs is in progress, the binding of the first section reinforcement for the elevator shaft has been completed. Earthwork continues, the previously compacted sand is being "blasted" for connecting the utilities, and other work is in progress too.
Alexander Sudarev, head of the information and analytics department, will tell about this and more in this video.
Enjoy watching!