"Sovelmash" D&E construction site | Day 176
In the new video from the construction site, you will see the changes that have taken place recently.
The construction of the firebreak represented by a wall of foam blocks has begun. The installation is carried out between the office and amenity building (O3333A) and the production part of the building. The following activities are in progress: the installation of the enclosing structures, namely the inner part of the walls; laying of the reinforcement mesh and the reinforcement frames, their further strapping and preparation for concrete casting of the interfloor slabs, as well as preparation for heating the next "map" for casting the 3rd floor interfloor slab.
Despite the bad weather, the builders are carrying out the work in accordance with the schedule, thanks to which we can see how the "Sovelmash" innovative center continues to "grow".