A tour of the engineering centre with Alexander Sudarev
Thanks to the good pace of funding, the construction has been accelerated. Would you like to see what construction activities are underway at the "Sovelmash" D&E today?
Watch the video with Alexander Sudarev.
• Doors have been installed in all the offices on the 1st floor of the office and amenity building. Glass partitions are installed, with some of them covered with frosted coating.
• The offices on the 1st floor of the O&A are almost fully settled in, with the 2nd floor to follow. Finishing work is now underway there. On the third floor, the construction workers are preparing to install interior glass partitions.
• Decorative wall and ceiling panels are being installed in the O&A.
• Sockets and switches are being installed.
• Fire cabinets have been connected.
• The amount of installed utilities in the workshop is growing by the day. The installation of ventilation and smoke extraction systems as well as heat insulation of hot water supply pipes are in full swing.
• The workshop is gradually being fitted with new equipment and connected to power supply.
The utmost effort is being made to complete and put the "Sovelmash" design and engineering technology department into operation as soon as possible.