Overview of the construction activities and equipment by Alexander Sudarev
"Sovelmash" is preparing in full swing to obtain the certificate of construction completion and launch production.
Watch a new video here.
• Nitrogen generators are being installed in the workshop.
• On the 1st floor of the office and amenity building the finishing is being completed, namely the installation of tiles and formation of sanitary facilities.
• Interior finishing continues on the 2nd floor of the O&A building with ventilation and fluorescent lighting being installed.
• On the third floor of the production area, the floor is about to be finished, dry screeding has been done, tiling has been installed in some premises, and heating radiators are being installed.
• Tiling and linoleum flooring has been laid on the second-floor mezzanine, enclosing structures have been installed, ventilation and air-conditioning systems are being mounted.
• The production workshop is packed with a variety of equipment, much of which has already been commissioned and is in operation.
Now "Sovelmash" is simultaneously pursuing two most critical tasks: to obtain the certificate of construction completion as soon as possible and to launch production at the D&E premises by the end of July 2024.
It is only possible to accomplish both tasks on time thanks to your active investment!