Key events of the week in the project "Duyunov's motors"
"Sovelmash" D&E construction
• Last week, the accommodation of the main administrative staff of "Sovelmash" in the premises of the D&E's first floor started. The offices "came to life": furniture, office machines and computers were put in place, the rooms were cleaned.
• Adjustment activities in the D&E's heat distribution unit were completed. It has been switched from manual to automatic control mode, i.e. heat consumption is now controlled by a meter. The premises of the heat distribution unit were thoroughly cleaned.
• Adjustment of the CNC machines began.
• The thermal insulation of the internal pipelines was started.
• Installation of glass partitions on the second floor in the office and amenity building started.
Now it is especially important to actively invest in the project in order to complete the construction as scheduled - by the end of March.
There are several offers available for you in the project right now. Their terms and conditions are available in the back office here.
The final round of the SOLARGROUP lottery continues, with every finalist having a chance to win an electric car.
Use it and make the most of your investment!