Week results in the project "Duyunov's motors"

Week results in the project "Duyunov's motors"

Over the past week, a ​significant amount of work was done at the construction site where the "Sovelmash" design and engineering technology department is currently being erected.

- The installation of the sealer and covering it with the final roofing elements continued.

- Casting the staircases in concrete was completed. This will enable covering the roof of the middle part of the building and completing the installation of the bulk of the roof.

- The 3rd floor is almost ready for casting the interfloor slabs: the profiled sheets have been sealed, the mezzanines are being sealed.

- On the 1st floor level, the work with the pits is nearing completion, the concrete work is being done, and the reinforcement frame is being strapped.

- On the territory of the temporary storehouse the number of enclosing structures has increased, their installation is being carried out.

Besides, the issue of connecting the heating system has been resolved. The heating equipment itself has already been manufactured, now it is necessary to solve a number of tasks to deliver and locate it on the construction site.

On the leased premises of "Sovelmash" in Zelenograd, work was also carried out in a number of areas.

- The tooling is being elaborated, which will increase the intensity and productivity of the automated production line.

- The tests of the angle grinders are progressing rapidly.

- The work with incremental encoders is being completed.

"Sovelmash" now needs the utmost support from the investors and partners in order to continue the D3333E construction on schedule. We offer you to familiarize yourself with the current profitable investment offers that will allow you not only to support the project, but also to invest with maximum profit. Descriptions of the offers are available in the project's back office here /user/ref/materials