Week results in the project "Duyunov's motors"
Over the past week, the construction of the "Sovelmash" design and engineering technology department has made significant progress. The following works were carried out at the "Alabushevo" site:
- sand backfilling of the pit with a layer-by-layer compaction,
- concreting the foundations of staircases,
- dismantling the formwork of previously cast concrete foundations,
- dismantling the formwork of staircases,
- waterproofing of foundations,
- installation of metal structures that make up the frame of the D3333E building.
The equipment for the automated production line was sent from China to Zelenograd. The "Sovelmash" team, and in particular the company's partner Victor Arestov, managed to produce equipment for the D3333E with the additional tooling and at the old prices, as well as to send it to Russia, despite the difficulties in the operation of Chinese ports.
To recap, the automated production line will be installed first on the leased premises of the company, and then relocated to the territory of the design and engineering technology department that is currently under construction. It will allow "Sovelmash" to produce small-scale batches of electric motors to demonstrate to the customers the opportunities of automated production for a specific motor model.
New, even more favorable conditions of the "Gift to a friend" option became available to the project participants. Until July 31 inclusive, invite a friend to the project, and each of you will receive 200 investment shares as a gift (previously the gift was 100 shares). You can do this on the main page of the back office. This way you will not only support the project and increase the number of your investment shares, but also give other people the opportunity to participate in the innovative project.