Results of the week in the project "Duyunov's motors"

Results of the week in the project "Duyunov's motors"

The territory of the "Sovelmash" construction site got even closer to its final appearance in the past week.

• The utility lines were installed from the building to the site where the climate control units would be located. Holes for the pipes in the concrete platform at the site were drilled.
• The workers started preparing the base for asphalt paving on the right side of the "Sovelmash" D&E building, where the heating pipeline runs.
• Inside the building, the internal engineering networks were being installed - namely, the electricity, heat and water supply lines. The water metering equipment and the pipework for the heat distribution unit equipment were being installed.
• The ventilation equipment was installed in the office and amenity building; the ceiling and upper utilities of the 1st floor were painted; and interior wall finishing was underway.
• Porcelain stoneware was installed in the passages, bathrooms and hallways of the 1st floor, and tiling was done in the medical facility.
• Concrete steps were cast for the exterior doors on the left side. The entrance to one of the gateways was also concreted there.

Representatives of the BAW car factory, including Vice General Manager Fedya Jia, visited the territory of the design and engineering technology department with a business-related mission.

The guests had a chance to meet Dmitriy Duyunov, the originator of the "Slavyanka" technology, and Sergey Semyonov, General Director of SOLARGROUP. They were introduced to the D&E capacities, held a business meeting and reached certain agreements.

The video about the visit is available here.