Results of the week in the project "Duyunov's motors"

Results of the week in the project "Duyunov's motors"

The construction of the "Sovelmash" design and engineering technology department proceeded on several fronts throughout the week.

• The landscaping of the area outside the "Sovelmash" site, where the utilities had previously been installed, reached completion. The kerbs and lawn pavement were restored.
• At the D&E site, the installation of heating pipe trays and the looping of all the utilities were in progress. A new shipment of pipes was delivered.
• The engineering networks inside the building were being installed. The wires were placed in special trays.
• The finishing work was carried out on the flights of stairs.
• Preparations were underway for installing the elevators.
• The commissioning and start-up of the equipment, in particular the induction motor production line, was underway.
• A new shipment of fire-resistant metal doors and gates for the production facility arrived.

We reported on the construction progress in more detail in the video here.

A number of offers are available in the project until May 31. Let us remind about them.

+5% shares bonus for newcomers.

+5% of the top-up amount.


Hurry up and take advantage of the beneficial investment conditions!

INVEST