Results of the week in the project "Duyunov's motors"

Results of the week in the project "Duyunov's motors"

The construction of the "Sovelmash" design and engineering technology department continued apace during the past week.

• The construction workers have reached the final stage of laying the engineering networks. The building is surrounded by water, sanitary and storm drainage pipes. All that remains is to loop these utilities in front of the main entrance to the building and then connect them to the existing networks of "Technopolis "Moscow".
• Exterior lighting and landscaping tasks have been prepaid. Excess soil is being removed from the site on the left side of the building and vertical levelling is already underway.
• Inside the building, the flights of stairs are being finished. The first of these has already been painted with finishing plaster. The steps have been tiled.
• The electrical distribution in the office and amenity building is fully completed.
• Auxiliary equipment has been fitted in the laboratory. Work is in progress on installing the utilities, connecting the chiller, electrics, etc.
• Both crane girders have been installed, in the workshop and in the laboratory.
• Work is underway in the winding area to connect the equipment.

The construction pace has been maintained largely thanks to the high level of investor activity in April. In May, it is important to maintain the project's funding target so that the D&E can be completed as scheduled.