Results of the week in the project "Duyunov's motors"
"Sovelmash" D&E construction
Work on the engineering utilities was in full swing outside and inside the building.
• Installing the heating pipeline to the design and engineering technology department building was underway. The trench was prepared. The installation of the pipes started.
• The builders dismantled part of the temporary road slabs in order to be able to connect the utilities to the building.
• A junction box was made for the cold water inlet to the building.
• The installation of interior partitions and electrical wiring continued.
• The property and equipment were moved from the leased premises to the D&E territory. The plan includes moving the "Sovelmash" testing laboratory to a new location by the end of 2022. This is necessary, among other things, in order to allocate the money saved on the rental of premises for construction.
Final webinar
On December 16, SOLARGROUP held a final webinar with Dmitriy Duyunov, Sergey Semyonov, Pavel Filippov, Alexander Sudarev, Victor Arestov, Andrey Lobov and other speakers. We summed up the 2022 results in the project and reported important news and plans for 2023.
Watch the final webinar recording here.
We remind you that there are less than two weeks left until the end of the year and the end of project funding stage 17. This means that the best time to buy a new investment package is up to and including December 31. As the project goes to stage 18 on January 1, the discount will go down.
In addition, until December 31, there is an offer to upsize a paid investment package. Learn more about it by following this link.
Until the end of the year, the project investors also participate in the New Year's lottery, getting the coupons that can win $ 15,000 and $ 1,000 investment packages. More details.
Support the "Sovelmash" D&E construction on beneficial conditions!